CML, Telford

We were appointed to undertake extensive building and external works improvements at this busy logistics facility following a lengthy tender and Value Engineering exercise.

The works comprised the construction of new two storey offices and staff canteen facilities, creation of new car parking and yard areas and extensive refurbishment of existing offices and yards. The works included the provision of new gatehouses, weighbridge, fuel storage and access controls – all whilst the facility remained open through the busiest time of the year.

New offices included a new canteen, bespoke glass partitions, combined heating and cooling system plus new changing and lockers areas. Externally the site was provided with new fencing and the existing drainage infrastructure was also improved.

Due to the nature of the works and the requirement to keep the business fully operational, the works were undertaken in 13 separate phases.

Project Specifications

Contract value: £2.6m

Start Date: May 2019

Completion Date: December 2019

Site Manager: Dave Fletcher